A restaurant build-out in Las Vegas runs in this order: secure the space and the landlord’s work letter, have plans drawn, get Southern Nevada Health District plan approval, get building and fire permits from the city or county covering your address, build and pass inspections, get a certificate of occupancy, then pass the health district’s final inspection before opening.
Each of those steps has its own reviewers, and most delays come from the handoffs between them. This guide walks through the sequence, what each agency asks for, the kitchen items that drive the design, and the things that most often slow an opening down. It reflects the published requirements of each agency as of November 2026. It is general information, not legal or code advice, so confirm your project with each agency before you build.
Step 1: What Should You Settle Before Signing the Lease?
The space decides a lot of your budget before any design starts. A former restaurant may already have a hood, a grease interceptor, floor sinks, and gas service. A former shop or office usually has none of that, and turning it into a restaurant is a change of use that the building department reviews as such. Clark County’s permit rules, for example, require a permit before anyone will “construct, enlarge, alter, repair, move, demolish or change occupancy” a building, or install or alter its electrical, gas, mechanical, or plumbing systems.
Before you sign, walk the space with your contractor and look at:
- Whether there is an existing hood and duct, and where a new duct could run through the roof.
- Whether the building has a grease interceptor, or room outside to install one.
- Gas service size, electrical panel capacity, and the rooftop HVAC units.
- Restrooms, the entry, and the parking area, since these affect ADA work.
- The age and condition of the existing kitchen equipment, if any stays.
Then read the landlord’s work letter closely. The work letter is the part of the lease that spells out what the landlord builds or pays for and what you build. It often sets the tenant improvement allowance, who handles the shell items such as the roof, utilities to the space, and the interceptor, and what the landlord must approve before you submit plans. Our guide to what a tenant improvement is covers how these lease terms usually work. The health district also asks for proof that you can operate at the address, such as the lease, so keep a signed copy handy.
Step 2: Who Draws the Plans, and What Do They Need to Show?
A restaurant needs drawings for two audiences: the building and fire departments, and the health district. The design team is usually an architect, mechanical, electrical, and plumbing (MEP) engineers, a kitchen equipment designer, and the fire suppression contractor for the hood system. Your general contractor should see the plans early, because layout choices change cost and schedule.
For the health district, the SNHD minimum requirements for plan submission list what a food or drink establishment sends in:
- A completed application packet and a contact person who can answer questions about the plans.
- Proof of ownership, such as a lease or deed, showing you can operate at the location.
- Plans in PDF showing the equipment layout and specifications, plumbing supply lines, waste lines, and fixtures, the finishes of floors, walls, and ceilings, and lighting.
- A menu, required for establishments with open-food handling.
- A Food Questionnaire, required for establishments that cook, cool, or reheat food.
The same document says every business needs a city or county business license and a business license with the Nevada Secretary of State before operating, and that the ownership on the health permit must match the business license. Start the licensing early so the names line up.
Step 3: How Does the Southern Nevada Health District Plan Review Work?
The Southern Nevada Health District (SNHD) Plan Review program processes new, remodel, and change of ownership health permit applications for food establishments and checks plans against the district’s regulations. Applications are submitted electronically through the district’s EH Portal and are processed in the order they are received.
Under the SNHD 2023 Food Regulations, Section 8-201.1, plans must be submitted for review and approval before the construction of a food establishment, the conversion of an existing building into one, or a remodel when the district decides plans are needed. Submit to the health district before you build, not after.
SNHD also publishes a guide to the top 10 general construction requirements for food establishments. A few that shape the design:
- Equipment must be NSF/ANSI certified or equivalent, with enough hot and cold holding for all foods.
- Floors, walls, and ceilings in food areas and restrooms must be smooth, durable, non-absorbent, and easily cleanable, with base coving where walls meet the floor.
- Lighting of 50 foot-candles in food handling areas, 20 in areas such as handwashing, warewashing, and restrooms, and 10 in walk-in coolers and dry storage.
- Outer doors that are solid, self-closing, and tight-fitting. Doors kept open for deliveries or trash usually need automatic air curtains.
- Waste lines not allowed over food preparation or storage areas unless separated in an approved way.
- Employee restrooms that do not open directly into food preparation or warewashing areas.
Step 4: Which Building Department Issues Your Permit?
It depends on the address, not the mailing city. The Las Vegas valley has four building departments, and each reviews plans, issues permits, and inspects its own projects:
- City of Las Vegas Building and Safety.
- City of Henderson Building and Fire Safety.
- City of North Las Vegas Building Safety.
- Clark County Department of Building and Fire Prevention, for unincorporated areas such as Paradise, Winchester, Spring Valley, and Enterprise.
A few points from their own pages. The City of Las Vegas says only a Nevada licensed contractor may obtain a building permit for commercial construction, that new commercial plans must be submitted electronically, and that some projects first go through zoning or other planning review. Henderson Building and Fire Safety issues permits and handles both building and fire plans checks. North Las Vegas Building Safety performs plan reviews, issues permits, and conducts inspections, issues certificates of occupancy electronically, and offers optional pre-construction meetings once plans and permits are approved.
If you are not sure which department covers your space, our guide on permits to remodel in Las Vegas explains how the jurisdictions split, and the building department can confirm your parcel before you apply.
Step 5: What Does the Fire Department Review for a Restaurant Kitchen?
Most of the fire review centers on the hood. Cooking equipment that produces grease-laden vapors under a Type I hood needs an automatic fire suppression system. The Clark County Fire Department permit guideline for commercial cooking extinguishing systems, dated January 2026, says a construction permit is required to install one and lists the standards it applies, including NFPA 96 (2024 edition) for ventilation and fire protection of commercial cooking, NFPA 17A (2021 edition) for wet chemical systems, and the 2024 International Fire Code with county amendments.
The same guideline spells out what the fire reviewer looks for:
- A pre-engineered wet chemical system tested to UL 300, with the manufacturer’s design manual named on the plans.
- Nozzle types, locations, and coverage, plus the hood filter bank type and hood, plenum, and duct dimensions.
- Every appliance under the hood, with dimensions and the spacing between them.
- Automatic fuel shut-off, the manual pull station location along the path out of the kitchen, and a connection to the building fire alarm if there is one.
- Plans signed by the contractor with the contractor’s license number and Nevada State Fire Marshal number.
Two notes matter for second-generation spaces. The guideline says any change to an existing wet chemical system needs a new submittal, including moving or adding appliances, changing cooking media, or changing the hood, plenum, or duct. It also says solid-fuel appliances such as wood smokers need their own hood and duct system, and grease ducts longer than 75 feet need sprinkler protection. If you plan to reuse an existing hood with a new menu, plan for a fire review anyway. Clark County is one example; the cities run their own fire plan reviews, so ask the department that covers your address what it requires.
Step 6: What Plumbing Does a Restaurant Need?
The health district’s construction guide and regulations set the main plumbing items for a food establishment:
- Handwashing sinks: wall-hung, located for convenient use in food prep and warewashing areas, sufficient in number, and reachable without opening doors or moving barriers.
- A three-compartment sink with a self-draining drainboard on each end wherever utensils are washed and sanitized, per Section 4-301.2 of the SNHD Food Regulations, with limited exceptions the regulation describes.
- At least one service sink or curbed cleaning area with a floor drain, such as a mop sink, with backflow protection.
- Indirect drain connections for sinks other than hand sinks and mop sinks, with floor sinks left exposed or easy to reach for cleaning.
- Vacuum breakers at hose bibs and anywhere back siphonage into the water line is possible.
Grease interceptors depend on the site. SNHD’s guide says fats, oils, grease, and grit must be kept out of the sewer, and that an outdoor in-ground grease interceptor must be installed when the building department or the water reclamation authority requires one. That makes the interceptor a question to ask before you sign, because adding one can mean cutting into the parking lot or the landlord’s site work.
Step 7: What About HVAC, Electrical, and Gas?
Restaurant kitchens put a heavy load on the mechanical and electrical systems. The exhaust hood pulls a large volume of air out of the building, so the HVAC design has to bring that air back in, and the hood system has to be coordinated with the rooftop equipment and the roof penetration for the duct. Cooking lines, walk-in coolers, ice machines, and dish machines add electrical and gas demand that older panels and gas meters may not cover.
These systems are reviewed with the building permit. The SNHD regulations also let the district ask for mechanical and plumbing schematics, equipment model numbers and capacities, and approvals from the building department, fire prevention, and the sewer authority as part of its own review, so the MEP drawings serve both reviews. Keep the equipment list consistent across every set of plans.
Step 8: How Does the ADA Apply to a Restaurant Build-Out?
A new restaurant build-out has to meet the 2010 ADA Standards for Accessible Design, along with the accessibility provisions in the building code your jurisdiction adopted. Two rules that shape a dining room:
- Section 226.1: where dining surfaces are provided, at least 5 percent of the seating and standing spaces at them must be accessible.
- Section 902.3: accessible dining surfaces must be 28 to 34 inches above the finish floor, with clear floor space and knee and toe clearance for a forward approach.
Remodels of an existing restaurant have one more rule. Under 28 CFR 36.403, the dining area is a primary function area, and altering it triggers work on the accessible path of travel to that area, including restrooms that serve it, unless the cost would be disproportionate, which the rule defines as more than 20 percent of the cost of the alteration.
Step 9: Which Inspections Come Before Opening?
During construction, the building department inspects the work in stages, typically framing, plumbing, electrical, mechanical, and finals, and the fire department inspects the hood suppression system and any fire alarm or sprinkler work. When the building and fire finals pass, the building department issues a certificate of occupancy or a temporary one.
The health district comes last. Its minimum requirements for final permitting inspections ask the person in charge to verify, before the inspection:
- Hand sinks with hot and cold running water, and working restrooms.
- Sewage disposal in place: floor sinks, drains, and the interceptor.
- Backflow protection, lighting, and equipment installed.
- Approved materials and finishes, with outer openings protected.
- All utilities working.
- As-built plans submitted to SNHD, including any changes made during construction.
- Approvals from other agencies as required, such as the TCO or CO, building approval, and fire approval.
- For food facilities, the three-compartment sink, utility sink, ventilation hood, grease interceptor in open-food facilities, adequate hot and cold holding and dry storage, the menu, and food handler cards.
Section 8-203 of the SNHD Food Regulations says the district conducts one or more preoperational inspections to confirm the restaurant was built and equipped according to the approved plans. Section 8-301 says no one may operate a food establishment without a valid permit to operate, and Section 8-302.1 says the permit application must be submitted at least 30 calendar days before the planned opening date.
What Slows a Restaurant Build-Out Down?
The common causes are predictable, which means most of them can be planned around:
- Signing a lease before checking the hood, interceptor, gas, and electrical capacity of the space.
- Incomplete submittals to the health district or building department, which send the plans back in the queue.
- Equipment changes after approval. A new fryer or a moved range can mean revised health district plans and a new fire suppression submittal.
- Drawings that disagree with each other, such as a different equipment list on the health and building sets.
- Landlord approvals that come late, especially for roof penetrations and site work.
- Long lead times on hoods, walk-ins, and rooftop units.
- Leaving the as-built plans and other agency approvals for the last week, when the health district asks for them before the final inspection.
A contractor who has built restaurants can check the space before you sign and keep one equipment list across every set of drawings. Butler’s builds retail and restaurant build-outs in Las Vegas, including commercial kitchens, hood systems, and restrooms, and coordinates the building and health department permits. Most of these projects are also tenant improvements in leased space, and remodels of operating restaurants run through our commercial remodeling work. If you are looking at a space, contact us with the address, the size, and your target opening date.
Sources
- Southern Nevada Health District: Plan Review
- SNHD: Minimum Requirements for Plan Submission
- SNHD: Top 10 General Construction Requirements for Food Establishments
- SNHD: Minimum Requirements for Final Permitting Inspections
- SNHD: 2023 Food Regulations
- Clark County Building and Fire Prevention: Do I Need a Permit?
- Clark County Fire Department: NFPA 17A Commercial Cooking Automatic Extinguishing Systems Permit Guideline
- NFPA 96: Ventilation Control and Fire Protection of Commercial Cooking Operations
- City of Las Vegas Building and Safety: Building and Offsite Permits
- City of Henderson: Building and Fire Safety
- City of North Las Vegas: Building Safety
- ADA.gov: 2010 ADA Standards for Accessible Design
- 28 CFR 36.403: Alterations, Path of Travel